Buffalo Hydraulic has been awarded a contract to design and build a custom bridge jacking system that will provide 24 points of lift.
Core samples determined that increasing decay was present at the point of contact between the bridge and the road foundation. To prevent a costly, and potentially dangerous safety situation, engineers decided to address the problem by jacking the bridge, removing and installing new pier supports at the entrance & exit to the bridge deck.
Located high above the Rogue River in the Cascade Mountains made this project especially picturesque. Because of the excessive mileage caused by re-routing any bridge traffic, this project had to be completed safely and without delay.
The bridge deck was lifted safely, evenly, and supported. The decaying piers were then removed and replaced. Traffic was then restored as was previously scheduled.
From NASA’s Kennedy Space Center to the mountains of the Pacific Northwest and from the Potomac River to Nicosia, Cypress and even to the extreme arctic conditions of Summit Greenland, Buffalo Hydraulic has the experience to make your most complex high tonnage project a success!
Please contact us today and we’ll be glad to make the safety and success of your upcoming project our top priority!