TENNESSEE VALLEY AUTHORITY (TVA)
Buffalo Hydraulic has been awarded a contract to design and build a hydraulic jacking system to be used in the re-construction of TVA’s Wilson Reservoir Dam on the Tenessee River in Muscle Shoals Alabama.
Construction on the Wilson Dam began in 1918 and was completed in 1924. Measuring 137′ high and 4,541′ wide, the Wilson Dam is the largest conventional hydro-electric plant in the TVA system. The maximum generating capacity of this site is 675,400 kilowatts.
We offer custom hydraulic jacking systems from one to several thousand tons and as many lifting points as your project requires. Our team is very grateful to the TVA for their confidence in our abilities. This project was very successful and was completed safely and far ahead of schedule.
From design to production, Buffalo Hydraulic has the ability to help with your next project!
Please contact us today and we’ll be glad to make the safety and success of your upcoming project our top priority!